Performance Analysis System Using Earned Value Method For Electrical Greenhouse Work Project In Batam City

Authors

  • Sally Lu Universitas International Batam, Indonesia
  • Mulia Pamadi Universitas International Batam, Indonesia

DOI:

https://doi.org/10.59141/jist.v4i12.828

Keywords:

cost, earned value method, time

Abstract

Infrastructure projects, such as greenhouse construction, are necessary for economic growth. Effective project control is essential, especially in managing budgets and ensuring timely completion. The Earned Value (EVM) method is used in construction project control because it integrates costs, time, and work progress. This allows for the identification of potential cost and time overruns. Data on expenditures and project-related documentation are gathered for analysis. Work plans and project schedules determine the value of work yet to be completed. The research findings up to the 10th month indicate that the projected total cost for completing the project is IDR 10,773,835,000. This leaves 8% of the total budgeted value as the remaining project budget. According to the data reported in the 11th month, the projected project completion time is 334 days. This is approximately 304 days ahead of the planned schedule. In summary, the EVM method is a valuable tool for project control in the construction industry. It can help to identify potential cost and time overruns and ensure that projects are completed on time and within budget.

Downloads

Published

2023-12-23

How to Cite

Lu, S., & Pamadi, M. . (2023). Performance Analysis System Using Earned Value Method For Electrical Greenhouse Work Project In Batam City. Jurnal Indonesia Sosial Teknologi, 4(12), 2288–2296. https://doi.org/10.59141/jist.v4i12.828